About Us
News & Prayer Letters
Mission Fields
Reformation Publications
Education
Donations
Downloads
Contact Us
Home
|
AND THEY BUILT THE WALLS:
After the foundation and floor was laid, steel pillars were set in place to help
share the load of the second story (block and cement), as well as provide
structure for the cement block walls.
SEPTEMBER, 2003
|
Pillars are placed every 8 feet throughout the structure. |
| Steel was used to provide greater strength in the
structure. This building is located about 80 feet away from a main road
which has heavy truck traffic from time to time. Whenever a fully loaded
truck goes down the road, the old house would vibrate slightly because of the
sandy soil and the high water table. |
 |
 |
The beams
are then placed on top of the pillars to spread the load of the second story
weight. For the present, the beams will not be covered by a ceiling,
saving ceiling costs. They will simply be painted. |
| Simultaneous to the installation of the beams,
the drainage system for the water run-off is being installed on the front side
of the building. |
 |
 |
In the back of the building, the septic tank for
the house and school is being built. Suriname does not have water
treatment plants, so the run-off from the septic goes into a canal system which
takes the water out to the river. For many years, this drained into
trenches on the school property, but those were later enclosed and pipes
installed to reroute it to the drainage ditches. |
| At long last, the actual walls begin with the
"laying of the first block" ceremony on September 15, 2003 (six months and seven
days after the fire). A cornerstone it is not, but in Suriname, the first
block is just about as significant. Rev. Rudy Poettcker (bending over with
trowel) and Rev. Asgar Hamid (squatting looking at the camera) partake of the
honors with a great portion of the school body partially noticeable in the
background. |
 |
 |
Blocks, blocks and more blocks are laid
throughout the structure for the completion of the block walls. The steel
pillars are slotted to receive the end of each row of blocks providing for a
much more stable securing of the wall than with a traditional cement pillar. |
| Walls along the back section overlook the
diagonal slab for the garage, over which a balcony for the residential portions
above will be situated. |
 |
 |
This picture demonstrates the method of cement
mixing used in 1982 when we built the school building seen below with the red
roof behind the ready-mix cement. First you lay down cement mixing bed
several days before. After that is hard, you put on it five wheelbarrow
loads of river gravel, then put three loads of river sand, and finally a number
of bags of cement. This is then dry mixed very well, backbreaking
shovel-full by shovel-full and shaped with high walls and a cleared center.
That is the easy part. Then water is added to the center and the walls are
systematically brought in for mixing until you have the right consistency of wet
cement (much heavier than when it was dry). From there it is offloaded by
shovel into the wheelbarrows and carted to wherever it is needed. |
|
With the progress of the situation in Suriname, ready-mixed
cement is generally cheaper and faster than in 1982, so the ready-mix trucks
keep the cement supplied for the large pouring jobs.
Block laying took all of September and part of October. |
 |
OCTOBER, 2003 October was primarily focused on plastering and much of
the electrical and plumbing work needed prior to the final plastering of the
walls.
| You are now looking down the main front hallway
where the workers are plastering the cement blocks walls. The plaster is
mixed by hand using white sand and cement. When mistakes were made, they
would tear the wall down and start again. A number of walls were plastered
more than once. Such things generally took place when the foreman was not
around. To the left (not seen) is the entrance to the
chapel. To the right, before the first door is the entrance to the school
reception area. The first door on the right is the main entrance to the
school offices. The later doors are for back entrances to the school
offices. At the end of the hall is the entrance to the school library and
some librarian and teacher offices. |
 |
NOVEMBER, 2003
 |
Here we see a man repairing portions of the
plaster on one of the office walls. |
| The building, viewed from one end with the front
to the left with the walls up. |
 |
After the wall is complete, the next stage is to ready the second floor
(first floor ceiling). Heavy corrugated steel will be laid over the
beams into which cement will be poured. In order to prepare for
carrying the weight of all the cement until it is cured, wood posts will be
placed upon the first level floor under the corrugated steel sheeting.
 |
2X4 lumber brought in for second floor supports. |
| Wood laid out inside the building in preparation
for supporting the second floor during the preparation and cement pouring and
curing stages. |
 |
 |
During the next week, the supports are set in place throughout
the building. The first floor is finally ready to be enclosed enabling the
interior work to begin irrespective of the weather conditions. |
To continue, click here to go to the next stage of the building process. While you are waiting for the new page, please pray for God to provide the finances needed to complete the rebuilding process.
6.
FIRST FLOOR SHELL COMPLETE November-December
2003
Return to top of page.
|